Cycle Hire was delayed until next month because councils refused planning permission

Darren Atwater | Thursday 17 June, 2010 12:36

Says Adam Bienkov

The scheme was meant to begin in May but has been pushed back after 75 of the 498 applications were blocked by individual councils.

It will now open next month but the Mayor admits that some stations will still not be completed before the launch.

Cycle Hire begins, allegedly, sources say, 30 July.